Big Plans for Mount Pleasant are Underway.

N. Main Street Closure for Waterline Project - March 26, 2025

Beginning April 2, North Main Street will be closed from Highway 49 to Cook Street for the Town's waterline replacement project. This section of North Main Street will be closed to through traffic for approximately 2 months as crews replace the lines. Access will be maintained for local traffic only to residences on N. Main Street. Mail, garbage collection, and yard debris collection will still be able to access residences on their regular schedule, but delays may occur.

[Read the rest of this article...]

Posted in: Infrastructure
Actions: E-mail | Permalink |
Cook Street Closure - March 11, 2025

The waterline tie-in at the intersection of Cook Street and N. Washington Street has been completed. Utility crews are now working on laying the new waterline along Cook Street from N. Washington Street to N. Main Street. Beginning Thursday, March 13 Cook Street will be closed from N. Main Street to the Gordon Funeral Home and Atrium-Cabarrus Family Medicine driveways.

[Read the rest of this article...]

Posted in: Infrastructure
Actions: E-mail | Permalink |
Lower Adams Creek Sewer Outfall Work to Begin - February 20, 2025

Work will begin on the Lower Adams Creek Sewer Outfall on Friday, February 21. This is earlier than the original start date of March 3 provided by the utility contractor. Workers will begin by clearing the right-of-way.  Map of project

[Read the rest of this article...]

Posted in: Infrastructure
Actions: E-mail | Permalink |
Contract to Replace Water Plant Components & Filter Media Approved - February 14, 2025

At its February 11 meeting, the Mount Pleasant Town Board of Commissioners approved a contract with WesTech/Swire Water (working with ClearWater Inc.) the entities that acquired the manufacturer (Neptune) of the Town's original early 1980s water treatment plant.  The proposal comes after 6 months of intensive water sampling/testing throughout the system and engineering necessary to determine the best course of action to upgrade the plant and improve water quality. 

[Read the rest of this article...]

Posted in: Infrastructure
Actions: E-mail | Permalink |
Road Closures for Infrastructure Projects - February 7, 2025 (updated Feb. 14)

Two different projects will result in brief road closures on Cook Street and S. Main Street over the next two weeks.  Beginning Sunday, February 16 through Friday, February 21, utility contractors will be working to replace four sewer manholes on S. Main Street between Franklin Street and Lee Street, resulting in closing S. Main Street to through traffic. During the week of Tuesday, February 24, 2025, utility contractors will close the eastern end of Cook Street at the intersection of N. Washington Street to start work on the Town's waterline project. Cook Street will be reopened by the end of the week (Feb. 28).  The work on Cook Street was postponed from the original schedule by two weeks due to rainy weather.

[Read the rest of this article...]

Posted in: Infrastructure
Actions: E-mail | Permalink |
New Water and Sewer Projects to Begin in February - February 5, 2025

On February 5, Town staff held a pre-construction meeting with project engineers and contractors for the Water Distribution Line project and Lower Adams Creek Outfall project.  State Utility Contractors of Monroe, NC will begin the Water Distribution Line project on Monday, February 10, 2025.  The water line project is scheduled to be completed by the end of 2025.  Elite Infrastructure Group of Monroe, NC will begin work the Lower Adams Creek Outfall line on Monday, March 3, 2025.  The sewer project is scheduled to be completed by March 2026.

[Read the rest of this article...]

Posted in: Infrastructure
Actions: E-mail | Permalink |
Manhole Replacement Continues on Lee Street & S. Main Street - January 24, 2025

The last few manholes to be replaced will take place over the next few weeks.  On Monday, January 27 and Tuesday, January 28, utility contractors will be working to replace a manhole on the western end of Lee Street.

[Read the rest of this article...]

Posted in: Infrastructure
Actions: E-mail | Permalink |
Sewer Line & Manhole Replacement Project Nears Completion - January 10, 2025

Utility contractors have been working since September on replacement of old clay sewer lines and manholes on C Street, Wade Street, Reid Street, A Street, and B Street.  The final leg of sewer line is being completed on B Street with manhole replacement at the intersection of E. Franklin Street (Hwy. 73) scheduled for the week of January 13.

[Read the rest of this article...]

Posted in: Infrastructure
Actions: E-mail | Permalink |
Funding Shortage Resolved and Contracts Awarded for Water & Sewer Projects - December 31, 2024

In December, the Town of Mount Pleasant awarded contracts to the lowest responsible bidders for the Lower Adams Creek Sewer Outfall Project and Water Distribution Improvements.  Work is expected to begin in Spring 2025.

[Read the rest of this article...]

Posted in: Infrastructure
Actions: E-mail | Permalink |
Sewer Line Work Continues on A Street and Reid Street - November 7, 2024

On Monday, November 11, sewer line replacement will begin on A Street and Reid Street. Work will continue for approximately 3-4 weeks. There will be a lane shift on Highway 73 (E. Franklin St.) for 2 days to make the tie in to the sewer main.

[Read the rest of this article...]

Posted in: Infrastructure
Actions: E-mail | Permalink |
Status of Project Construction Bids - October 3, 2024

The bid deadline for the Mount Pleasant Water Line Project and Lower Adams Creek Sewer Outfall Project was September 25, 2024.  The Sewer Outfall Project received five bids.  The Town and project engineer are currently performing due diligence to verify the lowest responsible bid.  The water line project only received two bids.  State law requires a minimum of three bids to open.  Therefore, the Water Line Project has been readvertised and bids will now be opened on October 16, 2024 at 2pm.

[Read the rest of this article...]

Posted in: Infrastructure
Actions: E-mail | Permalink |
Sewer Line Replacement to Close Lane on Hwy. 73 - September 25, 2024

As part of the sewer line work, traffic on East Franklin Street (NC Highway 73) will be reduced to one lane down to one lane in the vicintiy of C Street.  Work will begin Sunday, September 29, 2024 and will continue 24 hours a day for approximately one week.  The round the clock schedule has been approved by NCDOT in order to expedite the work and reduce the amount of time for the lane closure.

[Read the rest of this article...]

Posted in: Infrastructure
Actions: E-mail | Permalink |
Water and Sewer Projects Go to Bid - August 22, 2024

The long-awaited Mount Pleasant water line and Lower Adams Creek Sewer Outfall projects went out to bid this week.  Bid submittals are due September 25, 2024.  The Town Board of Commissioners is scheduled to accept the low bid at its October meeting and hopes to start the water line project by the end of the year. 

[Read the rest of this article...]

Posted in: Infrastructure
Actions: E-mail | Permalink |
Sewer Line and Manhole Replacement Underway - August 19, 2024

Utility contractor BRS Inc. is working on manhole and sewer line replacement.  During the week of August 12, two sewer manholes were replaced on Summer Street.  Beginning the week of August 19, BRS will mobilize on C Street and Wade Street to replace old clay sewer lines and a stormwater culvert on C street.

[Read the rest of this article...]

Posted in: Infrastructure
Actions: E-mail | Permalink |
Empire Drive Pump Station and Sewer Line Nearing Completion - August 2024

Utility contractor BRS, Inc. has made quick work of the Empire Drive Pump Station and force main sewer line along NC Highway 49.  The pump station and sewer line are on schedule to be operational in early September

[Read the rest of this article...]

Posted in: Infrastructure
Actions: E-mail | Permalink |
Page 1 of 2First   Previous   [1]  2  Next   Last