|
|
Posted on June 23, 2025 15:31
The Town’s waterline project continues to make progress. Crews are working on tie-ins to the new line and pavement restoration on N. Main Street between Cook Street and Highway 49. New water lines have also been installed from North Drive to Highway 49 along N. Main Street, as well as the western section of Crestwood Drive at the White Owl Antique Mall. Waterline is currently being installed on Highway 49 between Main Street and Highway 73. The waterline installation on Empire Drive was delayed several weeks. A new installation date has not be provided by the contractor yet. Waterline installation on Highway 73 (Franklin Street) will begin in July.
[Read the rest of this article...]
Posted on May 30, 2025 13:30
During the weeks of June 9 and June 16, contractors have scheduled the installation of a water line on Empire Drive (Hwy. 49 side). The waterline will be located outside of the travel lanes and within the street right-of-way on the north side of the street.
[Read the rest of this article...]
Posted on May 30, 2025 11:00
There is a brief planned water service interruption for water customers along Broad Street, Elm Street, N. College Street, and Historic Hill Drive on Monday, June 2 around 10am. This interruption will be approximately 30 minutes to test valves ahead of switching service over to the new waterline.
[Read the rest of this article...]
Posted on May 16, 2025 14:51
The utility contractor for the Lower Adams Creek Sewer Outfall line has notified the Town that, beginning the week of May 19, there will be occasional blasting (not expected more than once or twice a week) over the next several weeks as they encounter rock along Adams Creek.
[Read the rest of this article...]
Posted on May 16, 2025 14:47
Pressure and compaction testing have been successfully completed on Cook Street. Crews were scheduled to complete pavement restoration on Thursday and Friday May 15 & 16. Unfortunately due to an issue with equipment, final pavement restoration has been delayed to early in the week of May 19. Once this is done, waterline work is completed on Cook Street.
[Read the rest of this article...]
Posted on April 25, 2025 16:35
During the week of April 28, the waterline project contractor will be working on N. Main Street between Kluttz Street and Broad Street. While work is occurring in this area, the western ends of Kluttz Street and Broad Street may experience temporary closures to protect the work zone. Please use Jackson Street to access properties on Broad Street and Kluttz Street during this time.
[Read the rest of this article...]
Posted on April 08, 2025 16:05
Temporary road closures for two different utility projects will take place. The first is Circle Drive (behind Food Lion off of Duchess Drive) on Thursday, April 10 and Friday, April 11 (depending on weather) for a sewer line tie-in to retire the Food Lion pump station and connect to the new Empire Drive pump station. The second is on Elm Street (off of N. Main St.). As the waterline work moves up N. Main Street, the utility contractor needs to block Elm Street and N. College Street at MPCI Street to protect the migrating work zone. Once the work zone is beyond Elm Street, this section will reopen.
[Read the rest of this article...]
Posted on March 26, 2025 16:09
Beginning April 2, North Main Street will be closed from Highway 49 to Cook Street for the Town's waterline replacement project. This section of North Main Street will be closed to through traffic for approximately 2 months as crews replace the lines. Access will be maintained for local traffic only to residences on N. Main Street. Mail, garbage collection, and yard debris collection will still be able to access residences on their regular schedule, but delays may occur.
[Read the rest of this article...]
Posted on March 11, 2025 11:25
The waterline tie-in at the intersection of Cook Street and N. Washington Street has been completed. Utility crews are now working on laying the new waterline along Cook Street from N. Washington Street to N. Main Street. Beginning Thursday, March 13 Cook Street will be closed from N. Main Street to the Gordon Funeral Home and Atrium-Cabarrus Family Medicine driveways.
[Read the rest of this article...]
Posted on February 20, 2025 14:54
Work will begin on the Lower Adams Creek Sewer Outfall on Friday, February 21. This is earlier than the original start date of March 3 provided by the utility contractor. Workers will begin by clearing the right-of-way. Map of project
[Read the rest of this article...]
Posted on February 14, 2025 11:21
At its February 11 meeting, the Mount Pleasant Town Board of Commissioners approved a contract with WesTech/Swire Water (working with ClearWater Inc.) the entities that acquired the manufacturer (Neptune) of the Town's original early 1980s water treatment plant. The proposal comes after 6 months of intensive water sampling/testing throughout the system and engineering necessary to determine the best course of action to upgrade the plant and improve water quality.
[Read the rest of this article...]
Posted on February 07, 2025 16:07
Two different projects will result in brief road closures on Cook Street and S. Main Street over the next two weeks. Beginning Sunday, February 16 through Friday, February 21, utility contractors will be working to replace four sewer manholes on S. Main Street between Franklin Street and Lee Street, resulting in closing S. Main Street to through traffic. During the week of Tuesday, February 24, 2025, utility contractors will close the eastern end of Cook Street at the intersection of N. Washington Street to start work on the Town's waterline project. Cook Street will be reopened by the end of the week (Feb. 28). The work on Cook Street was postponed from the original schedule by two weeks due to rainy weather.
[Read the rest of this article...]
Posted on February 05, 2025 16:03
On February 5, Town staff held a pre-construction meeting with project engineers and contractors for the Water Distribution Line project and Lower Adams Creek Outfall project. State Utility Contractors of Monroe, NC will begin the Water Distribution Line project on Monday, February 10, 2025. The water line project is scheduled to be completed by the end of 2025. Elite Infrastructure Group of Monroe, NC will begin work the Lower Adams Creek Outfall line on Monday, March 3, 2025. The sewer project is scheduled to be completed by March 2026.
[Read the rest of this article...]
Posted on January 25, 2025 13:40
The last few manholes to be replaced will take place over the next few weeks. On Monday, January 27 and Tuesday, January 28, utility contractors will be working to replace a manhole on the western end of Lee Street.
[Read the rest of this article...]
Posted on January 10, 2025 13:46
Utility contractors have been working since September on replacement of old clay sewer lines and manholes on C Street, Wade Street, Reid Street, A Street, and B Street. The final leg of sewer line is being completed on B Street with manhole replacement at the intersection of E. Franklin Street (Hwy. 73) scheduled for the week of January 13.
[Read the rest of this article...]