On February 5, Town staff held a pre-construction meeting with project engineers and contractors for the Water Distribution Line project and Lower Adams Creek Outfall project. State Utility Contractors of Monroe, NC will begin the Water Distribution Line project on Monday, February 10, 2025. The water line project is scheduled to be completed by the end of 2025. Elite Infrastructure Group of Monroe, NC will begin work the Lower Adams Creek Outfall line on Monday, March 3, 2025. The sewer project is scheduled to be completed by March 2026.
The water line project will run new 12" water mains along the main corridors in Town including Main Street, Franklin Street (Hwy. 73), and NC Highway 49. This project will help to improve water quality and fire flow throughout the Town. The sewer line project will result in a sewer outfall along Adams Creek and will retire the antiquated Summer Street and Pasture Pump Stations.