Big Plans for Mount Pleasant are Underway.

Infrastructure Improvement Projects

The Town of Mount Pleasant is working on some important infrastructure projects.  Most of these projects implement portions of the Town's Water and Sewer Master Plan that was adopted in 2007 for which the Town has recently secured funding.

Empire Drive Sewer Pump Station and Sewer Line

Project Description:  This project will retire the old Mountainbrook and Food Lion Pump Stations and serve the new Brighton Park subdivision.  Click here to see a composite map of all proposed sewer improvements.

Schedule:  Work is scheduled to begin in the late spring of 2024 and be completed before spring 2025.   

Funding Source:  Portion of $6,048,000 USDA Low Interest Loan

Sewer Line and Manhole Rehabilitation (A, B, C, Wade, and Reid Streets)

Project Description:  This project will replace old clay sewer lines and manholes with new sewer lines and manholes along C Street, B Street, A Street, Wade Street, and Reid Street.  Click here to see a composite map of all proposed sewer improvements. 

Schedule:  Work is expected to begin at the end of August 2024 and be completed by December 2024.  Street paving is also part of this project.   

Funding Source:  Remainder of of $6,048,0000 USDA Low Interest Loan

Water Distribution Improvements (12-inch Water Mains)

Project Description:  This project will replace old 6-inch water lines (most installed in 1937) with new 12-inch water mains along Main Street (North Drive to Lee Street), Franklin Street (Skyland Drive to Blueberry Street), Cook Street (Main Street to N. Washington Street), and Highway 49 (Main Street to Highway 73 interchange).  This project will improve both water quality and fire flow throughout the Town. Click here to view the proposed improvements map.

Schedule:  This project is scheduled to begin February 10, 2025 with completion by the end of the year.

Funding Source:  $9,888,029 State Budget allocation from federal ARPA funds

Lower Adams Creek Sewer Outfall

Project Description:  This project was originally planned to be completed by the Water and Sewer Authority of Cabarrus County (WSACC) in 2009.  The project never came to fruition, so the Town is picking up the project where it left off.  This project will retire the Summer Street and Pasture pump stations.  .  Click here to view the proposed Lower Adams Creek Sewer Outfall map.  Click here to see a composite map of all proposed sewer improvements.

Schedule:  This project is scheduled to to begin March 3, 2025 with completion by March 2026.

Funding Source:  $5,822,971 State Budget allocation from federal ARPA funds

Water Intake & Treatment Improvements

Project Description:  The Town has been working with the North Carolina Department of Environmental Quality (NCDEQ) and three different consulting engineers to determine the necessary water intake and treatment upgrades and changes to improve drinking water quality and bring disinfection byproduct levels into compliance. 

Schedule:  A recommendation report is expected in Febrary 2025.  The implementation and installation of improvements will begin March 2025 and will take place in phases as funding is avalilable.

Funding Source:  $1,000,000 State Budget allocation from federal ARPA funds (redirected by technical correction in state budget from S. Skyland Drive/Allman Road extension water lines).  Additional funding is being pursued to complete needed improvements.

N. Washington Street Sidewalk

Project Description:  The Town adopted an NCDOT-funded Pedestrian Project Accleration Plan in 2020 and has been pursung funding to complete priority sidewalk segments since that time.  The first sidewalk project will complete 900 feet of sidewalk, curb & gutter on the southern end of N. Washington St. between Park Drive and E. Franklin Street.  This also includes a new stormwater culvert and slightly wider travel lanes.  Phase 2 on S. Washington Street is not included in this project.

N. Washington Street cut-sheet excerpt from Project Acceleration Plan

Schedule:  Engineering and permitting is currently underway.  The project is expected to go to bid in early May 2025.  Preparations are being made to either move or remove the house at 8563 E. Franklin Street (currently owned by the Town) to facilitate this project.

Funding Source:   In the state's 2023 budget, $2.7 million was directed to the Town of Mount Pleasant to complete priority sidewalk segments.

Franklin Street Sidewalks

Project Description:  The Town adopted an NCDOT-funded Pedestrian Project Accleration Plan in 2020 and has been pursung funding to complete priority sidewalk segments since that time.  There were three segments identified on Franklin Street:  Duchess Drive to Halifax Street, Halifax Street to Main Street, and Main Street to Blueberry Street.  The Town is working with NCDOT to design a project for one or more of these segments to stay within available funds.  Click here for excerpts from the Project Acceleration Plan.  Each segment is being evaluated for feasibility with available funds.

Franklin Street (Duchess Drive to Halifax Street) cut-sheet from Project Acceleration Plan

Franklin Street (Halifax Street to Main Street) cut-sheet from Project Acceleration Plan

Franklin Street (Main Street to Blueberry Street) cut-sheet from Project Acceleration Plan

Schedule:  The Town is currently working with NCDOT to determine which segments can be completed within available funds.  It is anticipated that at least one segment would begin in the 2025-26 fiscal year.  A extension will be needed to utilize designated funding.

Funding Source:  Remainder of $2.7 million after completion of N. Washington Street as a match with federal CMAQ/CRP grant funding.

Project Updates

Lower Adams Creek Sewer Outfall Work to Begin - February 20, 2025

Work will begin on the Lower Adams Creek Sewer Outfall on Friday, February 21. This is earlier than the original start date of March 3 provided by the utility contractor. Workers will begin by clearing the right-of-way.  Map of project

Contract to Replace Water Plant Components & Filter Media Approved - February 14, 2025

At its February 11 meeting, the Mount Pleasant Town Board of Commissioners approved a contract with WesTech/Swire Water (working with ClearWater Inc), the entities that acquired the manufacturer (Neptune) of the Town's original early 1980s water ...

Road Closures for Infrastructure Projects - February 7, 2025 (updated Feb. 14)

Two different projects will result in brief road closures on Cook Street and S. Main Street over the next two weeks.  During the week of February 24, 2025, utility contractors will close the eastern end of Cook Street at the intersection of N...

New Water and Sewer Projects to Begin in February - February 5, 2025

On February 5, Town staff held a pre-construction meeting with project engineers and contractors for the Water Distribution Line project and Lower Adams Creek Outfall project.  State Utility Contractors of Monroe, NC will begin the Water Distrib...

Manhole Replacement Continues on Lee Street & S. Main Street - January 24, 2025

The last few manholes to be replaced will take place over the next few weeks.  On Monday, January 27 and Tuesday, January 28, utility contractors will be working to replace a manhole on the western end of Lee Street. The end of Lee Street will b...

Sewer Line & Manhole Replacement Project Nears Completion - January 10, 2025

Utility contractors have been working since September on replacement of old clay sewer lines and manholes on C Street, Wade Street, Reid Street, A Street, and B Street.  The final leg of sewer line is being completed on B Street with manhole rep...

Funding Shortage Resolved and Contracts Awarded for Water & Sewer Projects - December 31, 2024

In December, the Town of Mount Pleasant awarded contracts to the lowest responsible bidders for the Lower Adams Creek Sewer Outfall Project and Water Distribution Improvements.  When the lowest bid for the Water Distribution Improvements came in...

Sewer Line Work Continues on A Street and Reid Street - November 7, 2024

On Monday, November 11, sewer line replacement will begin on A Street and Reid Street. Work will continue for approximately 3-4 weeks. There will be a lane shift on Highway 73 (E. Franklin St.) for 2 days to make the tie in to the sewer main. Sewer a...

Status of Project Construction Bids - October 3, 2024

The bid deadline for the Mount Pleasant Water Line Project and Lower Adams Creek Sewer Outfall Project was September 25, 2024.  The Sewer Outfall Project received five bids.  The Town and project engineer are currently performing due dilige...

Sewer Line Replacement to Close Lane on Hwy. 73 - September 25, 2024

Utility contractors have been making progress on the sewer line replacement project on the east side of Town and are nearing completion of C Street.  During the work, it was determined that the culvert under C Street was failing and needed to be...