Big Plans for Mount Pleasant are Underway.

Infrastructure Improvement Projects

The Town of Mount Pleasant is working on some important infrastructure projects.  Most of these projects implement portions of the Town's Water and Sewer Master Plan that was adopted in 2007 for which the Town has recently secured funding.

Empire Drive Sewer Pump Station and Sewer Line - COMPLETE

Project Description:  This project will retire the old Mountainbrook and Food Lion Pump Stations and serve the new Brighton Park subdivision.  Click here to see a composite map of all proposed sewer improvements.

Schedule:  Work is scheduled to begin in the late spring of 2024 and be completed before spring 2025.   

Funding Source:  Portion of $6,048,000 USDA Low Interest Loan

Sewer Line and Manhole Rehabilitation (A, B, C, Wade, and Reid Streets) - COMPLETE

Project Description:  This project will replace old clay sewer lines and manholes with new sewer lines and manholes along C Street, B Street, A Street, Wade Street, and Reid Street.  Click here to see a composite map of all proposed sewer improvements. 

Schedule:  Work is expected to begin at the end of August 2024 and be completed by December 2024.  Street paving is also part of this project.   

Funding Source:  Remainder of of $6,048,000 USDA Low Interest Loan

Water Distribution Improvements (12-inch Water Mains) - IN PROGRESS

Project Description:  This project will replace old 6-inch water lines (most installed in 1937) with new 12-inch water mains along Main Street (North Drive to Lee Street), Franklin Street (Skyland Drive to Blueberry Street), Cook Street (Main Street to N. Washington Street), and Highway 49 (Main Street to Highway 73 interchange).  This project will improve both water quality and fire flow throughout the Town. Click here to view the proposed improvements map.

Schedule:  This project is scheduled to begin February 10, 2025 with completion by the end of the year.

Funding Source:  $9,888,029 State Budget allocation from federal ARPA funds

Lower Adams Creek Sewer Outfall - IN PROGRESS

Project Description:  This project was originally planned to be completed by the Water and Sewer Authority of Cabarrus County (WSACC) in 2009.  The project never came to fruition, so the Town is picking up the project where it left off.  This project will retire the Summer Street and Pasture pump stations.  Click here to view the proposed Lower Adams Creek Sewer Outfall map.  Click here to see a composite map of all proposed sewer improvements.

Schedule:  This project is scheduled to to begin March 3, 2025 with completion by March 2026.

Funding Source:  $5,822,971 State Budget allocation from federal ARPA funds

Water Intake & Treatment Improvements -- IN PROGRESS

Project Description:  The Town has been working with the North Carolina Department of Environmental Quality (NCDEQ) and three different consulting engineers to determine the necessary water intake and treatment upgrades and changes to improve drinking water quality and bring disinfection byproduct levels into compliance.  All internal components and filter media the Water Treatment Plant are being replaced, a new Powder Activated Carbon (PAC) system is being engineered for installation, and the ground storage tank will be cleaned and coated.  The Town is also working towards supplementing raw water from Dutch Buffalo Creek with a well. 

Schedule:  Recommendations from engineering firms were provided in Febrary 2025.  The implementation and installation of improvements will begin March 2025 and will take place in phases as funding is avalilable.  The water treatment plant will be shut down to complete water treatement plant, PAC, and ground storage improvements in July and August of 2025.  Water will be purchased from the City of Concord during this time.

Funding Source:  $1,000,000 State Budget allocation from federal ARPA funds (redirected by technical correction in state budget from S. Skyland Drive/Allman Road extension water lines).  Additional funding is being pursued to complete needed improvements.

N. Washington Street Sidewalk - IN ENGINEERING

Project Description:  The Town adopted an NCDOT-funded Pedestrian Project Acceleration Plan in 2020 and has been pursuing funding to complete priority sidewalk segments since that time.  The first sidewalk project will complete 900 feet of sidewalk, curb & gutter on the southern end of N. Washington St. between Park Drive and E. Franklin Street.  This also includes a new stormwater culvert and slightly wider travel lanes.  Phase 2 on S. Washington Street is not included in this project.

N. Washington Street cut-sheet excerpt from Project Acceleration Plan

Schedule:  Engineering and permitting is currently underway.  The project is expected to go to bid late in 2025.  Preparations are being made to either move or remove the house at 8563 E. Franklin Street (currently owned by the Town) to facilitate this project.

Funding Source:   In the state's 2023 budget, $2.7 million was directed to the Town of Mount Pleasant to complete priority sidewalk segments.

Franklin Street Sidewalks - IN PRELIMINARY ENGINEERING

Project Description:  The Town adopted an NCDOT-funded Pedestrian Project Acceleration Plan in 2020 and has been pursuing funding to complete priority sidewalk segments since that time.  There were three segments identified on Franklin Street:  Duchess Drive to Halifax Street, Halifax Street to Main Street, and Main Street to Blueberry Street.  The Town is working with NCDOT to design a project for one or more of these segments to stay within available funds.  Click here for excerpts from the Project Acceleration Plan.  Each segment is being evaluated for feasibility with available funds.

Franklin Street (Duchess Drive to Halifax Street) cut-sheet from Project Acceleration Plan

Franklin Street (Halifax Street to Main Street) cut-sheet from Project Acceleration Plan

Franklin Street (Main Street to Blueberry Street) cut-sheet from Project Acceleration Plan

Schedule:  The Town is currently working with NCDOT to determine which segments can be completed within available funds.  It is anticipated that at least one segment would begin in the 2025-26 fiscal year.  A extension will be needed to utilize designated funding.

Funding Source:  Remainder of $2.7 million after completion of N. Washington Street as a match with federal CMAQ/CRP grant funding.

Project Updates

Waterline Project Progress Update - June 23, 2025

The Town’s waterline project continues to make progress. Crews are working on tie-ins to the new line and pavement restoration on N. Main Street between Cook Street and Highway 49. New water lines have also been installed from North Drive to Hi...

Empire Drive Water Line Installation - June 23, 2025 Status Update

Contractors had originally scheduled the installation of a waterline on Empire Drive (Hwy. 49 side) during the weeks of June 9 and June 16.  This work was postponed until additional progress is made on the main waterlines on Main Stree...

Planned Service Interruption - May 30, 2025

There is a brief planned water service interruption for water customers along Broad Street, Elm Street, N. College Street, and Historic Hill Drive on Monday, June 2 around 10am. This interruption will be approximately 30 minutes to test valves ahead ...

Completion of Waterline on Cook Street - May 16, 2025

Pressure and compaction testing have been successfully completed on Cook Street.  Crews were scheduled to complete pavement restoration on Thursday and Friday May 15 & 16.  Unfortunately due to an issue with equipment, final pavement re...

Waterline Project Work Between Kluttz St. & Broad St. - April 25, 2025

During the week of April 28, the waterline project contractor will be working on N. Main Street between Kluttz Street and Broad Street. While work is occurring in this area, the western ends of Kluttz Street and Broad Street may experience temporary ...

Elm Street and Circle Drive Closures - April 8, 2025

There are two road closure updates to share for two different utility projects: 1. Circle Drive (behind Food Lion off of Duchess Drive): There will be a brief road closure on Thursday, April 10 and Friday, April 11 (depending on weather) for a sew...

N. Main Street Closure for Waterline Project - March 26, 2025

Beginning April 2, North Main Street will be closed from Highway 49 to Cook Street for the Town's waterline replacement project. This section of North Main Street will be closed to through traffic for approximately 2 months as crews replace the l...

Cook Street Closure - March 11, 2025

The waterline tie-in at the intersection of Cook Street and N. Washington Street has been completed. Utility crews are now working on laying the new waterline along Cook Street from N. Washington Street to N. Main Street. Beginning Thursday, March 13...

Lower Adams Creek Sewer Outfall Work to Begin - February 20, 2025

Work will begin on the Lower Adams Creek Sewer Outfall on Friday, February 21. This is earlier than the original start date of March 3 provided by the utility contractor. Workers will begin by clearing the right-of-way.  Map of project

Contract to Replace Water Plant Components & Filter Media Approved - February 14, 2025

At its February 11 meeting, the Mount Pleasant Town Board of Commissioners approved a contract with WesTech/Swire Water (working with ClearWater Inc), the entities that acquired the manufacturer (Neptune) of the Town's original early 1980s water ...