Big Plans for Mount Pleasant are Underway.

The Town of Mount Pleasant is about to embark on several capital improvements projects to upgrade aging infrastructure. It has been 85 years since the Town’s first water lines were installed on Main and Franklin Streets. Their construction in 1937 allowed for the establishment of the Mount Pleasant Fire Department and construction of McAllister School, now Town Hall. 

Now Mount Pleasant is building on that foundation for it’s future. Over the next two years the Town will undertake the capital improvement project detailed within this site. 

Project Updates

McAllister Park Dedication June 24

McAllister Park Dedication June 24

We are excited to dedicate the McAllister Park Improvements that the Town has been working on for the past two years. McAllister Park has served the Mount Pleasant and Eastern Cabarrus community for more than 80 years

Fire Station Updates March 16

Fire Station Updates March 16

Fire Department Renovation/Addition:
Apparatus bay is complete, except for painting the walls and installing the Plymo Vent system, exterior walls are still being constructed, interior of the existing living quarters has been gutted with new electrical and plumbing rough-ins complete.  Estimated time for completion of project mid-summer 2023.

Park Project Updates March 16

Park Project Updates March 16

Concession stand is built, and the interior work is being completed, shingles will be added in the next two weeks, electrical conduit to be run from the concession stand to the electrical building, connecting sidewalk from the concession stand to the playground will be installed in the next few weeks, contractor and Town Staff are coordinating with Duke Energy on installation of the pedestrian lighting along the connecting sidewalk.  Estimated time of completion:  late Spring 2023

Fire Station Updates Jan 20

Fire Station Updates Jan 20

Footings are being poured off the front and back of station. Maybe some potential delays on the electrical panels based on delays occurring throughout the country. Exterior wall construction should start in the next few weeks.

Park Project Updates Jan 20

Park Project Updates Jan 20

Old Castle has been secured as the concrete block vendor. Concrete block has been delivered, and walls are going up! Site Contractor doing water/sewer work: material has been ordered. They should begin work end of next week or around January 23.

Town of Mount Pleasant Purchases Historic Henderson-Barrier House

Town of Mount Pleasant Purchases Historic Henderson-Barrier House

On Friday, the Town of Mount Pleasant purchased the historic Henderson-Barrier House located at 1431 N. Main Street from Ms. Kay Payne Beckett. As the oldest residence in Town, it is considered an important example of Greek Revival architecture.  The house is designated as a pivotal structure within the Mount Pleasant National Register Historic District, and the Town is committed to its long-term preservation.

Work to Begin at McAllister Ballfield

Work to Begin at McAllister Ballfield

Work at the McAllister Ballfield area will start Thursday, August 25, 2022. Town Hall, the Senior Center, and Food Ministry will be without power ALL DAY, Aug 25. Food Ministry will be open using generators, and Town Hall will operate from the Fire Department.