On Wednesday, February 25, the Town held its monthly project meeting with Elite Infrastructure to receive updates on the Lower Adams Creek Sewer Outfall project. Included in this update is a summary of the work that has been completed since last month and work that is currently underway.
Here is a summary of the work that has been completed since last month and work that is currently underway. The Town has been providing the information it has been given by contractors and engineers working on the project:
- All sewer line installation has be completed and tested
- Punch list items identified by WSACC have been completed.
- Pasture Pump Station and Summer Street Pump Station have been inverted and decommissioned and are in the process of being removed. The sewer outfall is now active.
- Gates installation where the easement meets roads was postponed, but will take place the first week of March.
- Soil and grass restoration will take place when the ground dries up from recent rain.