Big Plans for Mount Pleasant are Underway.

On Wednesday, January 28, the Town held its monthly project meeting with Elite Infrastructure to receive updates on the Lower Adams Creek Sewer Outfall project. 

Here is a summary of the work that has been completed since last month and work that is currently underway.  The Town has been providing the information it has been given by contractors and engineers working on the project:

  • All sewer line installation has be completed.  All sewer line has been tested.
  • Waiting on as-built palns to complete tie-ins and flow inversion for NCDEQ approval to remove Summer Street Pump Station and Pasture Pump Station.  Pasture Pump Station inversion will be completed first.
  • Native grass mix has been provided by Catawba Lands Conservancy to complete restoration at Buffalo Creek Preserve.
  • Gates for easement to be installed week of February 9.  
  • Substantial completion expected at end of February or beginning of March.
  • Restoration and punch list items identified by WSACC and inspectors to be completed.

Actions: E-mail