McAllister Park Dedication June 24

We are excited to dedicate the McAllister Park Improvements that the Town has been working on for the past two years. McAllister Park has served the Mount Pleasant and Eastern Cabarrus community for more than 80 years

[Read the rest of this article...]

Posted in: Town Park
Actions: E-mail | Permalink |
Park Project Updates March 16

Concession stand is built, and the interior work is being completed, shingles will be added in the next two weeks, electrical conduit to be run from the concession stand to the electrical building, connecting sidewalk from the concession stand to the playground will be installed in the next few weeks, contractor and Town Staff are coordinating with Duke Energy on installation of the pedestrian lighting along the connecting sidewalk.  Estimated time of completion:  late Spring 2023

[Read the rest of this article...]

Posted in: Town Park
Actions: E-mail | Permalink |
Park Project Updates Jan 20

Old Castle has been secured as the concrete block vendor. Concrete block has been delivered, and walls are going up! Site Contractor doing water/sewer work: material has been ordered. They should begin work end of next week or around January 23.

[Read the rest of this article...]

Posted in: Town Park
Actions: E-mail | Permalink |
Work to Begin at McAllister Ballfield

Work at the McAllister Ballfield area will start Thursday, August 25, 2022. Town Hall, the Senior Center, and Food Ministry will be without power ALL DAY, Aug 25. Food Ministry will be open using generators, and Town Hall will operate from the Fire Department.  