Oldenburg Street Paving - Update June 25,2026

Paving on Oberhaus Street and Waldeck Court are complete.  Due to extensive base repair needed on Erbach Lane, the project will take longer than anticipated.  The contractor will return the week of July 6 to complete resurfacing and backfill on Erbach Lane.  Marksburg Court will likely also be paved due to available funds and mobilization, since it is the only road in Oldenburg to not have previously been resurfaced.

[Read the rest of this article...]

Posted in: Infrastructure
Actions: E-mail | Permalink |
Waterline Project Monthly Update - June 25, 2026

On Wednesday, June 25, 2026, the Town held its monthly project meeting with State Utility Contractors to receive updates on the waterline project.   Included in this update is the status of each segment of the project.  A new waterline segment has been added to the project along Hwy. 49 and Jackson Street from the Water Treatment Plant to North Drive.  This project addition will take place from mid-July to September.  The chart and map at the end of this update show the status of each segment of the project

[Read the rest of this article...]

Posted in: Infrastructure
Actions: E-mail | Permalink |
Sewer Line and Manhole work on Hillside Drive, Ridge Avenue, and New Street - Update June 25, 2026

As an extension of the Lower Adams Creek Sewer Outfall project, approximately 215 feet of older sewer line and manholes will be replaced on Hillside Drive.  Project mobilization will begin the week of June 15.  Crews will also be replacing one manhole in Ridge Avenue and one manhole on New Street at the intersection of Ridge Avenue the week of June 20.  The work on Hillside Drive will begin the week of June 29.  All work is expected to take 4-6 weeks.  Road closure signs will be in place on Hillside Drive while work is occurring, but residents will be able to access their homes.  Please call Town Hall at 704-436-9800 if you have questions.

[Read the rest of this article...]

Posted in: Infrastructure