On Wednesday, October 29, the Town held its monthly project meeting with Elite Infrastructure to receive updates on the Lower Adams Creek Sewer Outfall project.
Here is a summary of the work that has been completed since last month and work that is currently underway. The Town has been providing the information it has been given by contractors and engineers working on the project:
- Blasting is complete
- Subtractor Young is working on completing the last bore under Adams Creek. Signficant rock is limiting progess to approximately 2 feet a day. Boring should be complete by early December.
- Once boring is complete, final sections of line will be installed.
- Testing of line continues along completed sections.
- Line installation should be by end of December with tie-ins to old Summer Street and Pasture pump station sites to be completed in Janauary.
Below is a map showing the project's progress. Sections highlighted in blue are complete. Sections highlighted in pink are currently being installed.