        <title>Mount Pleasant NC Future</title> 
        <link>https://mpncfuture.com</link> 
        <description>RSS feeds for Mount Pleasant NC Future</description> 
        <ttl>60</ttl> <item>
    <comments>https://mpncfuture.com/Dev/ID/1056/Park-Drive-Waterline-to-be-Installed--April-2-2026#Comments</comments> 
    <slash:comments>0</slash:comments> 
    <wfw:commentRss>https://mpncfuture.com/DesktopModules/DnnForge%20-%20NewsArticles/RssComments.aspx?TabID=55&amp;ModuleID=434&amp;ArticleID=1056</wfw:commentRss> 
    <trackback:ping>https://mpncfuture.com:443/DesktopModules/DnnForge%20-%20NewsArticles/Tracking/Trackback.aspx?ArticleID=1056&amp;PortalID=1&amp;TabID=55</trackback:ping> 
    <title>Park Drive Waterline to be Installed - April 2, 2026</title> 
    <link>https://mpncfuture.com/Dev/ID/1056/Park-Drive-Waterline-to-be-Installed--April-2-2026</link> 
    <description>A new 2-inch waterline will be installed along Park Drive on the Town Hall property to serve McAllister Park, the Lion&amp;#39;s Club, and the building that currently houses the Lunch Plus program. This will improve water volume to better serve these buildings. This project will affect traffic flow on Park Drive beginning Monday, April 6 through Friday, April 17.
</description> 
    <dc:creator>Erin Burris</dc:creator> 
    <pubDate>Thu, 02 Apr 2026 18:03:00 GMT</pubDate> 
    <guid isPermaLink="false">f1397696-738c-4295-afcd-943feb885714:1056</guid> 
    
</item>
<item>
    <comments>https://mpncfuture.com/Dev/ID/1055/Waterline-Project-Monthly-Update--March-27-2026#Comments</comments> 
    <slash:comments>0</slash:comments> 
    <wfw:commentRss>https://mpncfuture.com/DesktopModules/DnnForge%20-%20NewsArticles/RssComments.aspx?TabID=55&amp;ModuleID=434&amp;ArticleID=1055</wfw:commentRss> 
    <trackback:ping>https://mpncfuture.com:443/DesktopModules/DnnForge%20-%20NewsArticles/Tracking/Trackback.aspx?ArticleID=1055&amp;PortalID=1&amp;TabID=55</trackback:ping> 
    <title>Waterline Project Monthly Update - March 27, 2026</title> 
    <link>https://mpncfuture.com/Dev/ID/1055/Waterline-Project-Monthly-Update--March-27-2026</link> 
    <description>On Wednesday, March 25, the Town held its monthly project meeting with State Utility Contractors to receive updates on the waterline project.&amp;nbsp;&amp;nbsp; Included in this update is the status of each segment of the project.&amp;nbsp; The chart and map at the end of this update show the status of each segment of the project.
</description> 
    <dc:creator>Erin Burris</dc:creator> 
    <pubDate>Fri, 27 Mar 2026 15:12:00 GMT</pubDate> 
    <guid isPermaLink="false">f1397696-738c-4295-afcd-943feb885714:1055</guid> 
    
</item>
<item>
    <comments>https://mpncfuture.com/Dev/ID/1054/Lower-Adams-Creek-Sewer-Outfall-Project-Monthly-Update-February-26-2026#Comments</comments> 
    <slash:comments>0</slash:comments> 
    <wfw:commentRss>https://mpncfuture.com/DesktopModules/DnnForge%20-%20NewsArticles/RssComments.aspx?TabID=55&amp;ModuleID=434&amp;ArticleID=1054</wfw:commentRss> 
    <trackback:ping>https://mpncfuture.com:443/DesktopModules/DnnForge%20-%20NewsArticles/Tracking/Trackback.aspx?ArticleID=1054&amp;PortalID=1&amp;TabID=55</trackback:ping> 
    <title>Lower Adams Creek Sewer Outfall Project Monthly Update – February 26, 2026</title> 
    <link>https://mpncfuture.com/Dev/ID/1054/Lower-Adams-Creek-Sewer-Outfall-Project-Monthly-Update-February-26-2026</link> 
    <description>On Wednesday, February 25, the Town held its monthly project meeting with Elite Infrastructure to receive updates on the Lower Adams Creek Sewer Outfall project.&amp;nbsp; Included in this update&amp;nbsp;is a summary of the work that has been completed since last month and work that is currently underway. The sewer outfall is complete and active.&amp;nbsp; Restoration work is underway.&amp;nbsp;
</description> 
    <dc:creator>Erin Burris</dc:creator> 
    <pubDate>Thu, 26 Feb 2026 15:41:00 GMT</pubDate> 
    <guid isPermaLink="false">f1397696-738c-4295-afcd-943feb885714:1054</guid> 
    
</item>
<item>
    <comments>https://mpncfuture.com/Dev/ID/1053/Waterline-Project-Monthly-Update--February-26-2026#Comments</comments> 
    <slash:comments>0</slash:comments> 
    <wfw:commentRss>https://mpncfuture.com/DesktopModules/DnnForge%20-%20NewsArticles/RssComments.aspx?TabID=55&amp;ModuleID=434&amp;ArticleID=1053</wfw:commentRss> 
    <trackback:ping>https://mpncfuture.com:443/DesktopModules/DnnForge%20-%20NewsArticles/Tracking/Trackback.aspx?ArticleID=1053&amp;PortalID=1&amp;TabID=55</trackback:ping> 
    <title>Waterline Project Monthly Update - February 26, 2026</title> 
    <link>https://mpncfuture.com/Dev/ID/1053/Waterline-Project-Monthly-Update--February-26-2026</link> 
    <description>On Wednesday, February 25, the Town held its monthly project meeting with State Utility Contractors to receive updates on the waterline project.&amp;nbsp;&amp;nbsp; Included in this update is the status of each segment of the project.&amp;nbsp; The chart and map at the end of this update show the status of each segment of the project.
</description> 
    <dc:creator>Erin Burris</dc:creator> 
    <pubDate>Thu, 26 Feb 2026 15:25:00 GMT</pubDate> 
    <guid isPermaLink="false">f1397696-738c-4295-afcd-943feb885714:1053</guid> 
    <enclosure url="https://mpncfuture.com:443/Portals/1/Images/WaterIcon.png" length="9758" type="image/png" />
</item>
<item>
    <comments>https://mpncfuture.com/Dev/ID/1052/Side-Street-Tie-Ins-Continue-on-W-Franklin-St--February-6-2026#Comments</comments> 
    <slash:comments>0</slash:comments> 
    <wfw:commentRss>https://mpncfuture.com/DesktopModules/DnnForge%20-%20NewsArticles/RssComments.aspx?TabID=55&amp;ModuleID=434&amp;ArticleID=1052</wfw:commentRss> 
    <trackback:ping>https://mpncfuture.com:443/DesktopModules/DnnForge%20-%20NewsArticles/Tracking/Trackback.aspx?ArticleID=1052&amp;PortalID=1&amp;TabID=55</trackback:ping> 
    <title>Side Street Tie-Ins Continue on W. Franklin St. - February 6, 2026</title> 
    <link>https://mpncfuture.com/Dev/ID/1052/Side-Street-Tie-Ins-Continue-on-W-Franklin-St--February-6-2026</link> 
    <description>Utility contractors are working to complete side street tie-ins to the new waterline on W. Franklin Street.&amp;nbsp; Water service interruptions of approximately 3-5 hours are expected for each tie-in.&amp;nbsp; Please call Town Hall at 704-436-9800 with questions.&amp;nbsp; The following schedule has been provided by the contractor:


 Monday, February 9:&amp;nbsp; S. Halifax Street
 Tuesday, February 10:&amp;nbsp; Eagle Street &amp;amp; Page Street
 Wednesday, February 11:&amp;nbsp; Abbott Street &amp;amp; S. Skyland Drive (affects Abbott Street, Eagle Street, Pinecrest Drive, S. Skyland Drive, and Allman Rd. Extension)
 Thursday, February 12:&amp;nbsp; N. Skyland Drive

</description> 
    <dc:creator>Erin Burris</dc:creator> 
    <pubDate>Tue, 10 Feb 2026 19:39:00 GMT</pubDate> 
    <guid isPermaLink="false">f1397696-738c-4295-afcd-943feb885714:1052</guid> 
    
</item>
<item>
    <comments>https://mpncfuture.com/Dev/ID/1051/Lower-Adams-Creek-Sewer-Outfall-Monthly-Project-Update--January-29-2026#Comments</comments> 
    <slash:comments>0</slash:comments> 
    <wfw:commentRss>https://mpncfuture.com/DesktopModules/DnnForge%20-%20NewsArticles/RssComments.aspx?TabID=55&amp;ModuleID=434&amp;ArticleID=1051</wfw:commentRss> 
    <trackback:ping>https://mpncfuture.com:443/DesktopModules/DnnForge%20-%20NewsArticles/Tracking/Trackback.aspx?ArticleID=1051&amp;PortalID=1&amp;TabID=55</trackback:ping> 
    <title>Lower Adams Creek Sewer Outfall Monthly Project Update - January 29, 2026</title> 
    <link>https://mpncfuture.com/Dev/ID/1051/Lower-Adams-Creek-Sewer-Outfall-Monthly-Project-Update--January-29-2026</link> 
    <description>On Wednesday, January 28, the Town held its monthly project meeting with Elite Infrastructure to receive updates on the Lower Adams Creek Sewer Outfall project.&amp;nbsp; Included in this update&amp;nbsp;is a summary of the work that has been completed since last month and work that is currently underway. &amp;nbsp;The Town has been providing the information it has been given by contractors and engineers working on the project.
</description> 
    <dc:creator>Erin Burris</dc:creator> 
    <pubDate>Thu, 29 Jan 2026 17:53:00 GMT</pubDate> 
    <guid isPermaLink="false">f1397696-738c-4295-afcd-943feb885714:1051</guid> 
    
</item>
<item>
    <comments>https://mpncfuture.com/Dev/ID/1050/Waterline-Monthly-Project-Update--January-29-2026#Comments</comments> 
    <slash:comments>0</slash:comments> 
    <wfw:commentRss>https://mpncfuture.com/DesktopModules/DnnForge%20-%20NewsArticles/RssComments.aspx?TabID=55&amp;ModuleID=434&amp;ArticleID=1050</wfw:commentRss> 
    <trackback:ping>https://mpncfuture.com:443/DesktopModules/DnnForge%20-%20NewsArticles/Tracking/Trackback.aspx?ArticleID=1050&amp;PortalID=1&amp;TabID=55</trackback:ping> 
    <title>Waterline Monthly Project Update - January 29, 2026</title> 
    <link>https://mpncfuture.com/Dev/ID/1050/Waterline-Monthly-Project-Update--January-29-2026</link> 
    <description>On Wednesday, January 28, the Town held its monthly project meeting with State Utility Contractors to receive updates on the waterline project.&amp;nbsp;&amp;nbsp; Included in this update is the status of each segment of the project.&amp;nbsp; The chart and map at the end of this update show the status of each segment of the project.
</description> 
    <dc:creator>Erin Burris</dc:creator> 
    <pubDate>Thu, 29 Jan 2026 15:13:00 GMT</pubDate> 
    <guid isPermaLink="false">f1397696-738c-4295-afcd-943feb885714:1050</guid> 
    
</item>
<item>
    <comments>https://mpncfuture.com/Dev/ID/1049/Side-Street-Tie-Ins-on-W-Franklin-St-January-28-2026#Comments</comments> 
    <slash:comments>0</slash:comments> 
    <wfw:commentRss>https://mpncfuture.com/DesktopModules/DnnForge%20-%20NewsArticles/RssComments.aspx?TabID=55&amp;ModuleID=434&amp;ArticleID=1049</wfw:commentRss> 
    <trackback:ping>https://mpncfuture.com:443/DesktopModules/DnnForge%20-%20NewsArticles/Tracking/Trackback.aspx?ArticleID=1049&amp;PortalID=1&amp;TabID=55</trackback:ping> 
    <title>Side Street Tie-Ins on W. Franklin St.-January 28, 2026</title> 
    <link>https://mpncfuture.com/Dev/ID/1049/Side-Street-Tie-Ins-on-W-Franklin-St-January-28-2026</link> 
    <description>State Utility, the contractor for the waterline project, has informed the Town that on Thursday, January 29 and Friday, January 30 crews will be completing tie-ins to the side streets on W. Franklin Street. &amp;nbsp;Tie-ins will be completed at Halifax St., Summer Street, Hillside Drive, and College Street. &amp;nbsp;Service interruptions will occur on S. Halifax Street, Summer Street, Hillside Drive, New Street, Ludwig Street, Ridge Avenue, S. College Street and a portion of N. College Street for 3-5 hours for each of the four tie-ins, between 8am and 5pm on Thursday and Friday. &amp;nbsp;Please call Town Hall at 704-436-9800 if you have questions.&amp;nbsp;
</description> 
    <dc:creator>Erin Burris</dc:creator> 
    <pubDate>Thu, 29 Jan 2026 15:09:00 GMT</pubDate> 
    <guid isPermaLink="false">f1397696-738c-4295-afcd-943feb885714:1049</guid> 
    
</item>
<item>
    <comments>https://mpncfuture.com/Dev/ID/1048/Service-Tie-ins-on-W-Franklin-Street-Week-of-January-19#Comments</comments> 
    <slash:comments>0</slash:comments> 
    <wfw:commentRss>https://mpncfuture.com/DesktopModules/DnnForge%20-%20NewsArticles/RssComments.aspx?TabID=55&amp;ModuleID=434&amp;ArticleID=1048</wfw:commentRss> 
    <trackback:ping>https://mpncfuture.com:443/DesktopModules/DnnForge%20-%20NewsArticles/Tracking/Trackback.aspx?ArticleID=1048&amp;PortalID=1&amp;TabID=55</trackback:ping> 
    <title>Service Tie-ins on W. Franklin Street Week of January 19</title> 
    <link>https://mpncfuture.com/Dev/ID/1048/Service-Tie-ins-on-W-Franklin-Street-Week-of-January-19</link> 
    <description>State Utility, the contractor for the waterline project, has informed the Town that beginning Monday, January 19, crews will be completing service tie-ins to the new line for customers on W. Franklin Street. Each tie-in can result in service interruption of approximately 30 minutes for that customer. There is sometimes a bit of air/cloudiness after the connection is first made. Running an outside faucet for a few minutes will help clear air in the line.
</description> 
    <dc:creator>Erin Burris</dc:creator> 
    <pubDate>Fri, 16 Jan 2026 20:21:00 GMT</pubDate> 
    <guid isPermaLink="false">f1397696-738c-4295-afcd-943feb885714:1048</guid> 
    
</item>
<item>
    <comments>https://mpncfuture.com/Dev/ID/1047/Waterline-Project-Update--January-16-2026#Comments</comments> 
    <slash:comments>0</slash:comments> 
    <wfw:commentRss>https://mpncfuture.com/DesktopModules/DnnForge%20-%20NewsArticles/RssComments.aspx?TabID=55&amp;ModuleID=434&amp;ArticleID=1047</wfw:commentRss> 
    <trackback:ping>https://mpncfuture.com:443/DesktopModules/DnnForge%20-%20NewsArticles/Tracking/Trackback.aspx?ArticleID=1047&amp;PortalID=1&amp;TabID=55</trackback:ping> 
    <title>Waterline Project Update - January 16, 2026</title> 
    <link>https://mpncfuture.com/Dev/ID/1047/Waterline-Project-Update--January-16-2026</link> 
    <description>Monthly project meeting schedules were altered during November and December due to the holidays. &amp;nbsp;The next monthly project meeting is scheduled for January 28, but there has been a lot going on, so the Town wanted to go ahead and provide and update between meetings. &amp;nbsp;
</description> 
    <dc:creator>Erin Burris</dc:creator> 
    <pubDate>Fri, 16 Jan 2026 19:29:00 GMT</pubDate> 
    <guid isPermaLink="false">f1397696-738c-4295-afcd-943feb885714:1047</guid> 
    
</item>
<item>
    <comments>https://mpncfuture.com/Dev/ID/1046/Lower-Adams-Creek-Sewer-Outfall-Project-Update-December-12-2025#Comments</comments> 
    <slash:comments>0</slash:comments> 
    <wfw:commentRss>https://mpncfuture.com/DesktopModules/DnnForge%20-%20NewsArticles/RssComments.aspx?TabID=55&amp;ModuleID=434&amp;ArticleID=1046</wfw:commentRss> 
    <trackback:ping>https://mpncfuture.com:443/DesktopModules/DnnForge%20-%20NewsArticles/Tracking/Trackback.aspx?ArticleID=1046&amp;PortalID=1&amp;TabID=55</trackback:ping> 
    <title>Lower Adams Creek Sewer Outfall Project Update – December 12, 2025</title> 
    <link>https://mpncfuture.com/Dev/ID/1046/Lower-Adams-Creek-Sewer-Outfall-Project-Update-December-12-2025</link> 
    <description>On Wednesday, December 10, the Town held its monthly project meeting with Elite Infrastructure to receive updates on the Lower Adams Creek Sewer Outfall project.&amp;nbsp; The Town has been providing the information it has been given by contractors and engineers working on the project.&amp;nbsp;&amp;nbsp;The project is still on schedule to be substantially complete by the end of the year.&amp;nbsp; Included&amp;nbsp;is a summary of the work that has been completed since last month and work that is currently underway as well as a map showing progress.
</description> 
    <dc:creator>Erin Burris</dc:creator> 
    <pubDate>Fri, 12 Dec 2025 19:09:00 GMT</pubDate> 
    <guid isPermaLink="false">f1397696-738c-4295-afcd-943feb885714:1046</guid> 
    
</item>
<item>
    <comments>https://mpncfuture.com/Dev/ID/1045/Waterline-Project-Monthly-Update--December-12-2025#Comments</comments> 
    <slash:comments>0</slash:comments> 
    <wfw:commentRss>https://mpncfuture.com/DesktopModules/DnnForge%20-%20NewsArticles/RssComments.aspx?TabID=55&amp;ModuleID=434&amp;ArticleID=1045</wfw:commentRss> 
    <trackback:ping>https://mpncfuture.com:443/DesktopModules/DnnForge%20-%20NewsArticles/Tracking/Trackback.aspx?ArticleID=1045&amp;PortalID=1&amp;TabID=55</trackback:ping> 
    <title>Waterline Project Monthly Update - December 12, 2025</title> 
    <link>https://mpncfuture.com/Dev/ID/1045/Waterline-Project-Monthly-Update--December-12-2025</link> 
    <description>On Wednesday, December 10, the Town held its monthly project meeting with State Utility Contractors to receive updates on the waterline project.&amp;nbsp;&amp;nbsp; Included in this update is the status of each segment of the project.&amp;nbsp; The chart and map at the end of this update show the status of each segment of the project.
</description> 
    <dc:creator>Erin Burris</dc:creator> 
    <pubDate>Fri, 12 Dec 2025 18:34:00 GMT</pubDate> 
    <guid isPermaLink="false">f1397696-738c-4295-afcd-943feb885714:1045</guid> 
    
</item>
<item>
    <comments>https://mpncfuture.com/Dev/ID/1044/Lower-Adams-Creek-Sewer-Outfall-Project-Monthly-Update-October-29-2025#Comments</comments> 
    <slash:comments>0</slash:comments> 
    <wfw:commentRss>https://mpncfuture.com/DesktopModules/DnnForge%20-%20NewsArticles/RssComments.aspx?TabID=55&amp;ModuleID=434&amp;ArticleID=1044</wfw:commentRss> 
    <trackback:ping>https://mpncfuture.com:443/DesktopModules/DnnForge%20-%20NewsArticles/Tracking/Trackback.aspx?ArticleID=1044&amp;PortalID=1&amp;TabID=55</trackback:ping> 
    <title>Lower Adams Creek Sewer Outfall Project Monthly Update – October 29, 2025</title> 
    <link>https://mpncfuture.com/Dev/ID/1044/Lower-Adams-Creek-Sewer-Outfall-Project-Monthly-Update-October-29-2025</link> 
    <description>On Wednesday, October 29, the Town held its monthly project meeting with Elite Infrastructure to receive updates on the Lower Adams Creek Sewer Outfall project.&amp;nbsp; The Town has been providing the information it has been given by contractors and engineers working on the project.&amp;nbsp;&amp;nbsp;The project is still on schedule to be completed by the end of the year.&amp;nbsp; Included&amp;nbsp;is a summary of the work that has been completed since last month and work that is currently underway as well as a map showing progress.
</description> 
    <dc:creator>Erin Burris</dc:creator> 
    <pubDate>Thu, 30 Oct 2025 14:35:00 GMT</pubDate> 
    <guid isPermaLink="false">f1397696-738c-4295-afcd-943feb885714:1044</guid> 
    
</item>
<item>
    <comments>https://mpncfuture.com/Dev/ID/1043/Waterline-Project-Monthly-Update--October-29-2025#Comments</comments> 
    <slash:comments>0</slash:comments> 
    <wfw:commentRss>https://mpncfuture.com/DesktopModules/DnnForge%20-%20NewsArticles/RssComments.aspx?TabID=55&amp;ModuleID=434&amp;ArticleID=1043</wfw:commentRss> 
    <trackback:ping>https://mpncfuture.com:443/DesktopModules/DnnForge%20-%20NewsArticles/Tracking/Trackback.aspx?ArticleID=1043&amp;PortalID=1&amp;TabID=55</trackback:ping> 
    <title>Waterline Project Monthly Update - October 29, 2025</title> 
    <link>https://mpncfuture.com/Dev/ID/1043/Waterline-Project-Monthly-Update--October-29-2025</link> 
    <description>On Wednesday, October 29, the Town held its monthly project meeting with State Utility Contractors to receive updates on the waterline project.&amp;nbsp;&amp;nbsp; Included in this update is the status of each segment of the project.&amp;nbsp;&amp;nbsp;The chart and map at the end of this update show the status of each segment of the project.&amp;nbsp;&amp;nbsp;
</description> 
    <dc:creator>Erin Burris</dc:creator> 
    <pubDate>Wed, 29 Oct 2025 20:27:00 GMT</pubDate> 
    <guid isPermaLink="false">f1397696-738c-4295-afcd-943feb885714:1043</guid> 
    
</item>
<item>
    <comments>https://mpncfuture.com/Dev/ID/1042/N-Main-St-to-Open-W-Franklin-St-to-Close--October-17-2025#Comments</comments> 
    <slash:comments>0</slash:comments> 
    <wfw:commentRss>https://mpncfuture.com/DesktopModules/DnnForge%20-%20NewsArticles/RssComments.aspx?TabID=55&amp;ModuleID=434&amp;ArticleID=1042</wfw:commentRss> 
    <trackback:ping>https://mpncfuture.com:443/DesktopModules/DnnForge%20-%20NewsArticles/Tracking/Trackback.aspx?ArticleID=1042&amp;PortalID=1&amp;TabID=55</trackback:ping> 
    <title>N. Main St. to Open, W. Franklin St. to Close - October 17, 2025</title> 
    <link>https://mpncfuture.com/Dev/ID/1042/N-Main-St-to-Open-W-Franklin-St-to-Close--October-17-2025</link> 
    <description>N. Main Street in Mount Pleasant will reopen to through traffic the afternoon of Friday, October 17. Beginning the week of October 27, the waterline utility contractor will close W. Franklin Street (NC Hwy. 73) between Main Street and Halifax Street, as required by NCDOT. This section will be closed for approximately 8 weeks, while the waterline is installed. Access for local traffic and businesses in this section of W. Franklin Street will be maintained, but caution and patience will need to be exercised.
</description> 
    <dc:creator>Erin Burris</dc:creator> 
    <pubDate>Fri, 17 Oct 2025 16:55:00 GMT</pubDate> 
    <guid isPermaLink="false">f1397696-738c-4295-afcd-943feb885714:1042</guid> 
    
</item>
<item>
    <comments>https://mpncfuture.com/Dev/ID/43/Lower-Adams-Creek-Sewer-Outfall-Project-Update-September-24-2025#Comments</comments> 
    <slash:comments>0</slash:comments> 
    <wfw:commentRss>https://mpncfuture.com/DesktopModules/DnnForge%20-%20NewsArticles/RssComments.aspx?TabID=55&amp;ModuleID=434&amp;ArticleID=43</wfw:commentRss> 
    <trackback:ping>https://mpncfuture.com:443/DesktopModules/DnnForge%20-%20NewsArticles/Tracking/Trackback.aspx?ArticleID=43&amp;PortalID=1&amp;TabID=55</trackback:ping> 
    <title>Lower Adams Creek Sewer Outfall Project Update – September 24, 2025</title> 
    <link>https://mpncfuture.com/Dev/ID/43/Lower-Adams-Creek-Sewer-Outfall-Project-Update-September-24-2025</link> 
    <description>On Wednesday, September 24, the Town held its monthly project meeting with Elite Infrastructure to receive updates on the Lower Adams Creek Sewer Outfall project.&amp;nbsp; The Town has been providing the information it has been given by contractors and engineers working on the project.&amp;nbsp;&amp;nbsp;The project is still on schedule to be completed by the end of the year.&amp;nbsp; Included&amp;nbsp;is a summary of the work that has been completed since last month and work that is currently underway as well as a map showing progress.
</description> 
    <dc:creator>Erin Burris</dc:creator> 
    <pubDate>Wed, 24 Sep 2025 20:22:00 GMT</pubDate> 
    <guid isPermaLink="false">f1397696-738c-4295-afcd-943feb885714:43</guid> 
    
</item>
<item>
    <comments>https://mpncfuture.com/Dev/ID/42/Waterline-Project-Monthly-Update--September-24-2025#Comments</comments> 
    <slash:comments>0</slash:comments> 
    <wfw:commentRss>https://mpncfuture.com/DesktopModules/DnnForge%20-%20NewsArticles/RssComments.aspx?TabID=55&amp;ModuleID=434&amp;ArticleID=42</wfw:commentRss> 
    <trackback:ping>https://mpncfuture.com:443/DesktopModules/DnnForge%20-%20NewsArticles/Tracking/Trackback.aspx?ArticleID=42&amp;PortalID=1&amp;TabID=55</trackback:ping> 
    <title>Waterline Project Monthly Update - September 24, 2025</title> 
    <link>https://mpncfuture.com/Dev/ID/42/Waterline-Project-Monthly-Update--September-24-2025</link> 
    <description>On Wednesday, September 24, the Town held its monthly project meeting with State Utility Contractors to receive updates on the waterline project.&amp;nbsp;&amp;nbsp; Included in this update is the status of each segment of the project.&amp;nbsp;&amp;nbsp;The chart and map at the end of this update show the status of each segment of the project.&amp;nbsp;&amp;nbsp;
</description> 
    <dc:creator>Erin Burris</dc:creator> 
    <pubDate>Wed, 24 Sep 2025 19:41:00 GMT</pubDate> 
    <guid isPermaLink="false">f1397696-738c-4295-afcd-943feb885714:42</guid> 
    
</item>
<item>
    <comments>https://mpncfuture.com/Dev/ID/41/Main-Street-Waterline-Installation-to-Cross-Hwy-73--September-11-2025#Comments</comments> 
    <slash:comments>0</slash:comments> 
    <wfw:commentRss>https://mpncfuture.com/DesktopModules/DnnForge%20-%20NewsArticles/RssComments.aspx?TabID=55&amp;ModuleID=434&amp;ArticleID=41</wfw:commentRss> 
    <trackback:ping>https://mpncfuture.com:443/DesktopModules/DnnForge%20-%20NewsArticles/Tracking/Trackback.aspx?ArticleID=41&amp;PortalID=1&amp;TabID=55</trackback:ping> 
    <title>Main Street Waterline Installation to Cross Hwy. 73 - September 11, 2025</title> 
    <link>https://mpncfuture.com/Dev/ID/41/Main-Street-Waterline-Installation-to-Cross-Hwy-73--September-11-2025</link> 
    <description>On Monday, September 15, the utility contractor will be performing an open cut across NC Highway 73 (Franklin Street) to continue the installation of the Main Street Waterline. &amp;nbsp;The contractor has received approval from NCDOT for extended work hours that day in order to reduce the amount of time that the crew is working in the intersection. &amp;nbsp;Traffic control will involve a shifting lane closure and flagging with assistance from the Cabarrus County Sheriff&amp;#39;s Office. &amp;nbsp;Please be mindful as you approach and travel through this work zone.&amp;nbsp; Also, during the week of September 15, the line will cross the corner of the parking lot that serves Moose Pharmacy and Buddy&amp;rsquo;s Place. &amp;nbsp;Unfortunately, this will necessitate the parking lot entrance from S. Main Street and most of the parking area to the side of Moose Pharmacy and the front of Buddy&amp;rsquo;s will be closed.
</description> 
    <dc:creator>Erin Burris</dc:creator> 
    <pubDate>Thu, 11 Sep 2025 15:20:00 GMT</pubDate> 
    <guid isPermaLink="false">f1397696-738c-4295-afcd-943feb885714:41</guid> 
    
</item>
<item>
    <comments>https://mpncfuture.com/Dev/ID/40/Lower-Adams-Creek-Sewer-Outfall-Update--August-29-2025#Comments</comments> 
    <slash:comments>0</slash:comments> 
    <wfw:commentRss>https://mpncfuture.com/DesktopModules/DnnForge%20-%20NewsArticles/RssComments.aspx?TabID=55&amp;ModuleID=434&amp;ArticleID=40</wfw:commentRss> 
    <trackback:ping>https://mpncfuture.com:443/DesktopModules/DnnForge%20-%20NewsArticles/Tracking/Trackback.aspx?ArticleID=40&amp;PortalID=1&amp;TabID=55</trackback:ping> 
    <title>Lower Adams Creek Sewer Outfall Update - August 29, 2025</title> 
    <link>https://mpncfuture.com/Dev/ID/40/Lower-Adams-Creek-Sewer-Outfall-Update--August-29-2025</link> 
    <description>On Wednesday, August 27, the Town held its monthly project meeting with Elite Infrastructure to receive updates on the Lower Adams Creek Sewer Outfall project.&amp;nbsp; The Town has been providing the information it has been given by contractors and engineers working on the project.&amp;nbsp;&amp;nbsp;The project is still on schedule to be completed by the end of the year.&amp;nbsp; Included&amp;nbsp;is a summary of the work that has been completed since last month and work that is currently underway as well as a map showing progress.

&amp;nbsp;
</description> 
    <dc:creator>Erin Burris</dc:creator> 
    <pubDate>Fri, 29 Aug 2025 19:40:00 GMT</pubDate> 
    <guid isPermaLink="false">f1397696-738c-4295-afcd-943feb885714:40</guid> 
    
</item>
<item>
    <comments>https://mpncfuture.com/Dev/ID/39/Waterline-Project-Update--August-29-2025#Comments</comments> 
    <slash:comments>0</slash:comments> 
    <wfw:commentRss>https://mpncfuture.com/DesktopModules/DnnForge%20-%20NewsArticles/RssComments.aspx?TabID=55&amp;ModuleID=434&amp;ArticleID=39</wfw:commentRss> 
    <trackback:ping>https://mpncfuture.com:443/DesktopModules/DnnForge%20-%20NewsArticles/Tracking/Trackback.aspx?ArticleID=39&amp;PortalID=1&amp;TabID=55</trackback:ping> 
    <title>Waterline Project Update - August 29, 2025</title> 
    <link>https://mpncfuture.com/Dev/ID/39/Waterline-Project-Update--August-29-2025</link> 
    <description>On Wednesday, August 27, the Town held its monthly project meeting with State Utility Contractors to receive updates on the waterline project. Please be mindful that the Town has been providing the information it has been given by contractors, engineers, and NCDOT.&amp;nbsp; Included in this summary the status of each segment of the project.&amp;nbsp; The current schedule and progress map are also included.
</description> 
    <dc:creator>Erin Burris</dc:creator> 
    <pubDate>Fri, 29 Aug 2025 14:06:00 GMT</pubDate> 
    <guid isPermaLink="false">f1397696-738c-4295-afcd-943feb885714:39</guid> 
    
</item>
<item>
    <comments>https://mpncfuture.com/Dev/ID/38/Waterline-Work-on-Main-Street-between-Cook-Street-and-Lee-Street--August-15-2025#Comments</comments> 
    <slash:comments>0</slash:comments> 
    <wfw:commentRss>https://mpncfuture.com/DesktopModules/DnnForge%20-%20NewsArticles/RssComments.aspx?TabID=55&amp;ModuleID=434&amp;ArticleID=38</wfw:commentRss> 
    <trackback:ping>https://mpncfuture.com:443/DesktopModules/DnnForge%20-%20NewsArticles/Tracking/Trackback.aspx?ArticleID=38&amp;PortalID=1&amp;TabID=55</trackback:ping> 
    <title>Waterline Work on Main Street between Cook Street and Lee Street - August 15, 2025</title> 
    <link>https://mpncfuture.com/Dev/ID/38/Waterline-Work-on-Main-Street-between-Cook-Street-and-Lee-Street--August-15-2025</link> 
    <description>At this time, State Utility is working on N. Main Street between Walnut Street and Park Drive, and this section of Main Street is closed to everyone except residents. Town Hall, McAllister Park, the Lion&amp;#39;s Club, and the Cabarrus County Lunch Plus Program are all currently accessible on Park Drive from N. Washington Street only. The Public Parking Lot adjacent to the Lentz Building is still accessible from N. Main Street at this time, but may experience brief closures at this entrance over the next two weeks while crews are actively working.
</description> 
    <dc:creator>Erin Burris</dc:creator> 
    <pubDate>Fri, 15 Aug 2025 17:23:00 GMT</pubDate> 
    <guid isPermaLink="false">f1397696-738c-4295-afcd-943feb885714:38</guid> 
    
</item>
<item>
    <comments>https://mpncfuture.com/Dev/ID/37/Waterline-Project-Update-July-31-2025#Comments</comments> 
    <slash:comments>0</slash:comments> 
    <wfw:commentRss>https://mpncfuture.com/DesktopModules/DnnForge%20-%20NewsArticles/RssComments.aspx?TabID=55&amp;ModuleID=434&amp;ArticleID=37</wfw:commentRss> 
    <trackback:ping>https://mpncfuture.com:443/DesktopModules/DnnForge%20-%20NewsArticles/Tracking/Trackback.aspx?ArticleID=37&amp;PortalID=1&amp;TabID=55</trackback:ping> 
    <title>Waterline Project Update – July 31, 2025</title> 
    <link>https://mpncfuture.com/Dev/ID/37/Waterline-Project-Update-July-31-2025</link> 
    <description>On Wednesday, July 30 the Town held its monthly project meeting with State Utility Contractors to receive updates on the waterline project.&amp;nbsp; Here is a summary of the status of each segment of the waterline project. Please be mindful that the Town has been providing the information it has been given by contractors, engineers, and NCDOT.&amp;nbsp; This is a complex project in which field conditions can result in delays and alterations in work and schedules.&amp;nbsp; Thank you for your continued patience during this once-in-a-lifetime project that has been in the works since 2007.&amp;nbsp; If you have questions, please contact Town Hall at 704-436-9800.
</description> 
    <dc:creator>Erin Burris</dc:creator> 
    <pubDate>Thu, 31 Jul 2025 18:40:00 GMT</pubDate> 
    <guid isPermaLink="false">f1397696-738c-4295-afcd-943feb885714:37</guid> 
    
</item>
<item>
    <comments>https://mpncfuture.com/Dev/ID/36/Lower-Adams-Creek-Sewer-Outfall-Project-Update-July-31-2025#Comments</comments> 
    <slash:comments>0</slash:comments> 
    <wfw:commentRss>https://mpncfuture.com/DesktopModules/DnnForge%20-%20NewsArticles/RssComments.aspx?TabID=55&amp;ModuleID=434&amp;ArticleID=36</wfw:commentRss> 
    <trackback:ping>https://mpncfuture.com:443/DesktopModules/DnnForge%20-%20NewsArticles/Tracking/Trackback.aspx?ArticleID=36&amp;PortalID=1&amp;TabID=55</trackback:ping> 
    <title>Lower Adams Creek Sewer Outfall Project Update – July 31, 2025</title> 
    <link>https://mpncfuture.com/Dev/ID/36/Lower-Adams-Creek-Sewer-Outfall-Project-Update-July-31-2025</link> 
    <description>On Wednesday, July 30 the Town held its monthly project meeting with Elite Infrastructure to receive updates on the Lower Adams Creek Sewer Outfall project. &amp;nbsp;Here is a summary of the work that has been completed since last month and work that is currently underway.&amp;nbsp; The Town has been providing the information it has been given by contractors and engineers working on the project.
</description> 
    <dc:creator>Erin Burris</dc:creator> 
    <pubDate>Thu, 31 Jul 2025 18:23:00 GMT</pubDate> 
    <guid isPermaLink="false">f1397696-738c-4295-afcd-943feb885714:36</guid> 
    
</item>
<item>
    <comments>https://mpncfuture.com/Dev/ID/35/Voluntary-Water-Conservation-Requested--July-17-2025#Comments</comments> 
    <slash:comments>0</slash:comments> 
    <wfw:commentRss>https://mpncfuture.com/DesktopModules/DnnForge%20-%20NewsArticles/RssComments.aspx?TabID=55&amp;ModuleID=434&amp;ArticleID=35</wfw:commentRss> 
    <trackback:ping>https://mpncfuture.com:443/DesktopModules/DnnForge%20-%20NewsArticles/Tracking/Trackback.aspx?ArticleID=35&amp;PortalID=1&amp;TabID=55</trackback:ping> 
    <title>Voluntary Water Conservation Requested - July 17, 2025</title> 
    <link>https://mpncfuture.com/Dev/ID/35/Voluntary-Water-Conservation-Requested--July-17-2025</link> 
    <description>The time has arrived. On Monday, July 21, the Town&amp;rsquo;s water plant operations will shut down for approximately two months in order to perform the necessary maintenance and improvements to resolve issues with organics and disinfection byproducts. While the connection with Concord will be able to provide adequate water for regular usage, the cost to provide the water during this time period will be higher than the amount that it costs for the Town to produce water for its customers. Additionally, tank levels are being constantly monitored to ensure that adequate water is available for both usage and fire flow for both Concord and Mount Pleasant. The Town requests that water customers exercise voluntary conservation efforts and limit water usage to what is absolutely necessary during this time.
</description> 
    <dc:creator>Erin Burris</dc:creator> 
    <pubDate>Thu, 17 Jul 2025 19:49:00 GMT</pubDate> 
    <guid isPermaLink="false">f1397696-738c-4295-afcd-943feb885714:35</guid> 
    
</item>
<item>
    <comments>https://mpncfuture.com/Dev/ID/34/Waterline-Project-Progress-Update--June-23-2025#Comments</comments> 
    <slash:comments>0</slash:comments> 
    <wfw:commentRss>https://mpncfuture.com/DesktopModules/DnnForge%20-%20NewsArticles/RssComments.aspx?TabID=55&amp;ModuleID=434&amp;ArticleID=34</wfw:commentRss> 
    <trackback:ping>https://mpncfuture.com:443/DesktopModules/DnnForge%20-%20NewsArticles/Tracking/Trackback.aspx?ArticleID=34&amp;PortalID=1&amp;TabID=55</trackback:ping> 
    <title>Waterline Project Progress Update - June 23, 2025</title> 
    <link>https://mpncfuture.com/Dev/ID/34/Waterline-Project-Progress-Update--June-23-2025</link> 
    <description>The Town&amp;rsquo;s waterline project continues to make progress. Crews are working on tie-ins to the new line and pavement restoration on N. Main Street between Cook Street and Highway 49. New water lines have also been installed from North Drive to Highway 49 along N. Main Street, as well as the western section of Crestwood Drive at the White Owl Antique Mall.&amp;nbsp; Waterline is currently being installed on Highway 49 between Main Street and Highway 73.&amp;nbsp; The waterline installation on Empire Drive was delayed several weeks.&amp;nbsp; A new installation date has not be provided by the contractor yet.&amp;nbsp; Waterline installation on Highway 73 (Franklin Street) will begin in July.
</description> 
    <dc:creator>Erin Burris</dc:creator> 
    <pubDate>Mon, 23 Jun 2025 19:31:00 GMT</pubDate> 
    <guid isPermaLink="false">f1397696-738c-4295-afcd-943feb885714:34</guid> 
    
</item>
